2.5. Changing a variable midway through an inverse proportion question

N2. Ratio and proportion

Question

Twelve workers are hired to build a wall in 9 days, assuming that they all work at the same rate. After 3 days, two workers left. How many days would the remaining workers take to finish building the wall?

Solution